Example
33 : NYSDOT-DEC Deer Carcass Composting – Practice
Guidelines
1. Choose a well-drained site with minimal slope,
at least 200 feet from water courses or other hydrologically
sensitive landscape features including streams and
wetlands. Separation distances should be 500 feet from
a residence and 200 feet from a property line. Siting
should also consider prevailing winds and aesthetic
impacts on neighbors.
2. Composting bin or windrow should be placed on
a hard surface made of paved asphalt, concrete, or
compacted millings. The pad needs to provide a good
working surface in all weather conditions and protection
of ground water. Sufficient amounts of amendments should
be added to piles to minimize the movement of liquids
( blood, etc.) from the carcasses. Any liquid that
leaves the pad must be absorbed in woodchips or other
acceptable materials and must be kept away from sensitive
areas ( streams etc.) .
3. Prepare a foundation layer of wood chips or recycled
deer compost in the bottom of the windrow or bin before
adding carcasses. This initial layer should be 18-24
inches deep. Sufficient quantities of woodchips and/or
finished compost must be at the site before any carcasses
arrive to ensure the piles can be formed in a timely
manner.
4. Place deer carcasses back to back in a single
layer on the foundation leaving at least 6 inches between
the carcasses and the bin walls. Completely surround
and cover the carcasses with at least 6 inches of damp
wood chips or recycled deer compost. If there are not
sufficient carcasses for a full layer, cover the edges
of the available carcasses with at least 6 inches of
wood chips or recycled deer compost and begin adding
carcasses at that point as they become available. Never
leave any part of a carcass exposed even if extra wood
chips or recycled deer compost must be added.
5. Continue this layering procedure until a windrow
or bin is full. The last layer used to cap the bin
should be 24 inches of wood chips or recycled deer
compost. This layer should curtail odors and dissuade
scavengers. Do not stack windrows/bins over 6 feet
high. A temperature rise in the compost pile to 125
degrees F or higher indicates that the process is working.
6. Allow the pile to remain idle for several months.
The pile can be broken down sooner, if the carcasses
are clearly fully degraded. The internal temperature
of the pile should be 120F to 150F during the active
composting phase. For pathogen reduction, it must be
shown that the carcass achieved a temperature of 131/F
or greater for three consecutive days. The temperature
probe used must be able to record temperatures in the
areas of the pile where the carcasses are located.
7. Once the material is fully composted, it can
be reused in starting new compost piles or used within
a highway right-of-way with appropriate setbacks. DEC
approval will be required for uses outside of the compost
area.
FACILITY REQUIREMENTS
- Suitable site allowing for setbacks
- Hard surface made of asphalt, concrete or compacted
millings for compost windrow OR
- Compost bins on asphalt, concrete or compacted
millings work pads
- Sufficient supply of wood chips
- Provisions for monitoring temperatures within
the compost pile. ( Thermocouple probe, thermister
probe or similar device may be used.)
- Rubber gloves and face masks
- Loader
- Water
- Before composting, contact the DOT Maintenance
Environmental Coordinator ( MEC) .
FACILITY CONTROLS
The compost piles will be segregated from other
facility operations, utilities, farming activities
and main traffic areas. A sign designating the compost
pile as such will be clearly visible at each compost
area. The sign may state "Deer Carcass Compost."
All workers at the assigned locations should be
made aware of the compost windrow or bin. Safety instructions
will be given via classroom or field setting.
PERSONNEL TRAINING
The Highway Maintenance Supervisor assigned to the
yard where the composting facility is located will
inform all yard employees of the composting facility.
All yard employees will be made aware of safety precautions
required.
Employees working with the compost will be informed
of the Operations and Maintenance procedures described
herein.
LOADING PROCEDURES
Deer typically get collected by manually lifting
the carcass into the back of a pick-up truck. While
the first carcasses may be added to the fresh compost
pile manually, any subsequent additions should be added
via heavy equipment, such as a loader. It is allowable
to park the pick-up truck as close as possible to the
compost pile and manually place the carcass from the
truck to the pile, as long as workers will not have
to step onto the compost pile. Woodchips should be
added via heavy equipment or off a pick-up truck. As
it may be challenging to place the deer back to back
with heavy equipment, the boards on one side of the
bins should be removable to make loading and unloading
the bins easier.
HANDLING INSTRUCTIONS
Handling of the compost pile will be accomplished
via heavy equipment.
Handling of the compost should be performed in a
manner that would prevent dispersion of the compost
material on the ground and prevent dispersion of compost
particles in the air.
COMPOST MANAGEMENT
A carcass may be added to the compost pile as ordered
by the Resident Engineer. In general, any deer collected
from the roadside may be added to the composting facility
as long as it does not show any overt signs of disease.
A deer that appears emaciated or showed untypical behavior
prior to becoming killed should not be added to the
compost pile as it may be diseased. Emaciated deer
should be reported to NYSDEC Wildlife Pathology Unit
in Albany ( Phone number 518/478-3032) for testing.
Through the trial composting effort, DOT will be
able to determine how many deer carcasses each compost
bin/windrow can handle within a given time frame. Potentially,
each composting bin could handle up to 30 carcasses
per composting effort, depending on the size of the
work pad. Compost windrows, extended lengthwise, would
be able to accommodate more carcasses. Each composting
bin/windrow can accept up to three layers of carcasses
to a maximum height of 6 feet.
The first layer should consist of 18-24" of
woodchips, followed by a layer of carcasses. Carcasses
should be placed back to back. This arrangement aids
in achieving higher composting temperatures. The carcasses
should be covered by 6" of woodchips. Repeat this
process until three layers are complete. Finish top
layer with 24" of woodchips. For windrows, repeat
this process in 10-15 foot long sections, adding on
to the existing windrow.
The moisture content of the pile contributes to
proper composting temperatures. The moisture content
of the wood chips or recycled deer compost added to
the mix should be about 60 percent, which is the point
where a handful of the material will just begin to
stay together when squeezed ( wear rubber gloves if
it is compost!) .
- The wood chips or recycled deer compost should
have the proper moisture content before adding it
to the bin/windrow. It is difficult to uniformly add
water to the mix in the composter.
- If the material falls apart after being squeezed,
it is too dry. Water should be sprinkled and mixed
into the wood chips.
- If free water drips from the squeezed material,
or if a film of free water is left on the hand, the
material is too wet. The material should be spread
to air dry or mixed with drier material to lower the
moisture content before adding to the compost mix.
- If a compost pile does not properly heat, it is
probably too wet or too dry or was filled improperly.
RECORDKEEPING
Compost monitoring and record keeping is necessary
in order to document proper functioning of the compost
pile. If dysfunction is evident, steps can be taken
to correct poor conditions. Compost monitoring will
let DOT learn more about the composting process and
create optimal composting conditions in the future.
- Any deer composting activities must be approved
by NYSDEC.
- Record the number of carcasses added to the pile
along with date.
- Temperatures within the compost pile will be monitored
and recorded once a day. A sample data log sheet is
attached for use. See Temperature Monitoring section.
- Odors should be recorded daily. Indicate whether
there are odors disseminating in the downwind direction
and if an odor is present, estimate how many feet
downwind it is noticeable.
- State when last carcass was added.
TEMPERATURE MONITORING
Proper composting requires sustained elevated temperatures
( 120F -170F) . High temperatures also achieve desired
pathogen reduction and a physically stabilized compost
material at the end of the process. Ideally, a continuous
temperature monitoring device should be utilized. A
thermocouple probe, thermistor probe or similar device
can be embedded in the compost pile. This device should
be connected to a lead wire and data logger, where
temperature variations can be recorded over a period
of time.
- A temperature probe ( bimetal thermometer) with
a four foot extension may also be used.
- The probe should be placed so that readings are
taken at 12"-36" from the top of the pile
in areas where the carcasses are located. As the pile
grows, the probe will need to be repositioned.
SAMPLING PLAN
Testing of finished compost will document the presence
of certain pathogens and ascertain what re-use the
compost product is suitable for. Sampling parameters
include pathogenic organisms and pathogen indicator
organisms. The Maintenance Environmental Coordinator
will be in charge of sampling. Within 3 months after
start-up of the project, a compost sampling and analysis
plan will be submitted to DEC for approval. Parameters
to be analyzed may include total coliform, fecal coliform,
E.coli, Salmonella, Cryptosporidium, total carbon and
total Kjehldal nitrogen. Bacteria causing Lyme disease
will not survive temperatures above 130F and as long
as composting achieved proper temperatures, testing
for this pathogen will not be necessary.
RECYCLING OF FINAL COMPOST PRODUCT
Material that is fully composted may be re-used
as a base for a new compost pile. Compost that has
been determined safe by inspection of records and the
sampling analysis, can be land applied within the highway
right-of-way subject to DEC approval.
CONTINGENCY PLAN
If any activity does not go according to plan, contact
the Resident Engineer. In the event that problems develop
which result or may result in environmental or public
health impacts or nuisance conditions, the compost
operation should be suspended and corrective measures
should be taken to mitigate impacts. Problems which
will trigger implementation of the contingency plan
will include, but not be limited to, odors detected
beyond the facility boundary, animals scavenging in
the compost piles or receipt of deer carcasses at a
rate which exceeds the handling capacity of the compost
facility. Corrective measures will include, but not
be limited to, covering with additional woodchips and/or
addition of lime to control odors, fencing the area
to prevent access by animals, temporarily covering
the piles with a tarp, cessation of operation until
the adverse impacts have been mitigated and, if other
measures fail, removal and disposal of the pile contents
by pit burial in accordance with applicable DEC regulations
and DOT guidelines or disposal of pit contents at an
approved solid waste management facility.
CLOSURE PLAN
The Maintenance Environmental Coordinator ( MEC)
is contacted before composting is started and needs
to be contacted in order to officially close out a
composting activity. The MEC will schedule a site visit
at that time, possibly with NYSDEC. Composting records
should be made available at that time and elements
of the process should be discussed. At that time it
should be determined, whether composting appears complete
and final sampling should be ordered. If yes, the MEC
will initiate the sampling process. Sampling results
and monitoring records will be provided to NYSDEC.
Depending on results, the compost will be recommended
for re-use as composting amendment or determined to
be suitable as a soil amendment.
If the finished compost will be used as soil amendment,
the site approval by the MEC and by DEC is required.
To permanently close a composting site, bins should
be disassembled and taken to a landfill. The workpad
may be kept for other uses, but must be decontaminated
using a 5 percent or 10 percent solution of sodium
hypochlorite ( household bleach) in water. The MEC
and NYSDEC will be notified that the deer composting
facility has been discontinued.
PERSONAL PROTECTION
Employees should follow the personal protective
equipment requirements outlined in the Rabies Safety
Bulletin 92-1 ( attached) when working with any road
kill. The safety bulletin recommends that rubber gloves
be worn. Questions in regard to the Safety Bulletin
should be directed to the Regional Safety Officer (
see Contact Information) . If a worker will be in immediate
contact with the compost for the purpose of taking
a temperature reading or other, personal protective
equipment, such as rubber gloves. Disposable face mask
should be available and worn at the discretion of the
employee.
Emaciated deer or deer showing untypical behaviors
( either alive or before becoming roadkill) should
be reported to NYSDEC Wildlife Pathology Unit in Albany
( Phone number 518/478-3032) . Do not add animals other
than deer to the compost!
ENVIRONMENTAL CONTROLS
Environmental quality will be addressed by carefully
choosing a site ( see Guidelines II.1.) . In order
to ensure proper site selection, the Maintenance Environmental
Coordinator should conduct a site screening via a physical
walk-over.
To ensure that the active compost pile does not
pose risks not addressed through proper setbacks, the
following should be considered:
- If nuisance vectors, such as flies etc are attracted
to the pile, more woodchips should be added to cover
the pile.
- Any leachate that may have puddled around the
pile needs to be absorbed by woodchips and adequately
covered.
- Odors would also indicate that additional woodchip
coverage is necessary.
Experiences of various entities utilizing composting
has shown that carnivorous animals will not be attracted
to compost piles as long as the pile is adequately
covered.
Prior to releasing the finished compost product
to the environment, monitoring records such as the
temperature logs and pile records will be reviewed.
The temperature log will indicate whether the material
has properly composted and whether the temperature
necessary for pathogen kill was reached. The operators
of the pile should ensure that adequate temperatures
are reached as outlined in the Guidelines. Composting
shall not be considered complete unless adequate temperature
data is collected after addition of the last carcass
to demonstrate that a minimum temperature of 131 F
has been reached and maintained for a minimum of three
consecutive days. The final sampling test results will
also determine the safety of the compost.
STAFFING PLAN AND CONTACT INFORMATION
The Highway Maintenance Supervisor II assigned to
the yard is responsible for day to day operations,
monitoring and proper functioning of the compost pile.
Correspondence, composting performance evaluation,
procedural guidance and sampling will be coordinated
by the Maintenance Environmental Coordinator.
Elisabeth Kolb, Maintenance Environmental Coordinator
Tel. 845/575-6158
|