Ditches,
berms, dikes and swales are temporary or permanent
measures used to intercept and direct surface runoff
to an overside/slope drain or stabilized watercourse,
away from the road. Several variations of ditch treatments
include raised curbs, berms, vegetated, rock-lined,
and lead out ditches. Raised curbs, or berms, are used
to prevent water from entering or exiting the roadway.
Numerous lead out ditches are typically installed to
remove water impounded by the curbs and release it
where water can be handled appropriately, with minimal
resource damage.
Ditch treatments can be used on roadsides, trails,
parking areas, urban and rural settings, and any other
place where managing runoff is important. A scoured,
entrenched roadside ditch and the presence of gullying
on the downslope side are indicators that a ditch treatment
may be necessary. Ditches, berms, dikes and swales
are usually implemented for the following purposes:
- To convey flow around maintenance activities.
- To divert flow away from maintenance stockpiles.
- At the top of slopes to divert run-on from adjacent
slopes and areas.
- At bottom and mid-slope locations to intercept
sheet flow and convey concentrated flows.
- At other locations to convey runoff to overside/drains,
stabilized watercourses, stormwater drainage system
inlets (catch basins), pipes and channels.
- To intercept runoff from paved surfaces.
- Along roadways and facilities subject to flood
drainage.
Vegetated ditches are ditches with vegetation
to reduce water velocities, and erosion control grass
mixtures are typically used to vegetate ditches. Vegetated
ditches help improve the quality of stormwater that
runs off a highway by slowing water velocities and
trapping sediment, metals, nutrients, petroleum products,
pesticides, bacteria and other contaminants.
Lead out ditches are built to carry water
away from the roadway, onto grassed or forested areas,
allowing infiltration and dispersion of water. Rock
or stone-lined ditches reduce velocities and capture
sediment in the interstices. Maintenance cleaning is
required when trash or debris have accumulated.
Temporary diversion dikes are intended to
divert overland sheet flow to a stabilized outlet or
a sediment trapping facility during establishment of
permanent stabilization on sloping, disturbed areas.
When used at the top of a slope, the structure protects
exposed slopes by keeping upland runoff away. When
used at the base of a slope, the structure protects
adjacent and downstream areas by diverting sediment-laden
runoff to a sediment trapping facility. This practice
is considered an economical one because it uses material
available on the site and can usually be constructed
with equipment needed for site grading. The useful
life of the practice can be extended by stabilizing
the dike with vegetation.
Design and Construction
Considerations and Practices for Ditches, Dikes, and
Swales
Caltrans has an excellent Fact
Sheet on Earth Dikes/Drainage Swales and Lined Ditches available
on-line, which provides implementation guidance, drawings,
specifications, and maintenance considerations. The
EPA and Florida DOT have online information on permanent
diversions and diversions.
Diversions are preferable to other types of constructed
stormwater conveyance systems because they more closely
simulate natural flow patterns and characteristics.
Flow velocities are generally kept to a minimum. Recommended
environmental stewardship practices for implementation
of ditches, berms, drains, swales, and diversions
include: [N]
Evaluate risks due to erosion, overtopping, flow
backups or washout.
Consider outlet protection where localized scour
is anticipated.
- Examine the site for run-on from off-site sources.
- Conveyances should be lined if high flow velocity
is anticipated. Consider use of riprap, engineering
fabric, asphalt concrete, or concrete.
- Establish adequate vegetation as soon as possible
after installation of a diversion.
- Stabilize the drainage area above the diversion
so that sediment will not enter and accumulate in
the diversion channel.
- Diversions should be constructed before clearing
and grading operations begin. If used to protect a
flat, exposed area, a diversion might be constructed
as a dike or berm. Berms made of gravel or stone can
be crossed by construction equipment.
- Diversions should have stabilized outlets which
will convey concentrated runoff without erosion. Acceptable
outlets include paved
flumes, stormwater
conveyance channels, outlet
protection, and level
spreaders. Outlets should be constructed and
stabilized prior to the operation of the diversion.
- Disturbed areas draining into the diversion should
be seeded and mulched prior to or at the time the
diversion is constructed.
- Permanent diversions should include a filter strip
of close growing grass maintained above the channel.
The width of the filter strip, measured from the center
of the channel, should be one-half the channel width
plus 15 feet (4.5 m).
- Unless otherwise stabilized, the ridge and channel
should be seeded and mulched within 15 days of installation
in accordance with permanent
seeding .
- If the diversion dike is going to remain in place
for longer than 30 days, it is very important that
it be established with temporary or permanent vegetation.
- The slope behind the dike is also an important
consideration. If the channel slope is less than or
equal to 2 percent, stabilization may not be required.
If the slope is greater than 2 percent, the channel
should be stabilized in accordance with BMPs for stormwater
conveyance channels.
- Whenever feasible, the dike should be built before
construction begins on the project.
- The dike should be adequately compacted to prevent
failure.
- The dike should be located to minimize damages
by construction operations and traffic.
Slope Diversions for Intercepting
Stormwater
Diversions are channels constructed across a slope
with a supporting ridge on the lower side, to reduce
slope length and to intercept and divert stormwater
runoff to stabilized outlets at non-erosive velocities.
On moderately sloping areas, they may be placed at
intervals to trap and divert sheet flow before it has
a chance to concentrate and cause rill and gully erosion.
Diversions may be placed at the top of cut or fill
slopes to keep runoff from upland drainage areas off
the slope. They can also be used to protect structures,
parking lots, adjacent properties, and other special
areas from flooding.
Diversions are often constructed:
- Where runoff from higher areas may damage property,
cause erosion, or interfere with the establishment
of vegetation on lower areas.
- Where surface and/or shallow subsurface flow is
damaging upland slopes.
- Where the slope length needs to be reduced to minimize
soil loss.
- Below stabilized or protected areas. They should
not be used below high sediment producing areas unless
land treatment practices or structural measures, designed
to prevent damaging accumulations of sediment in the
channels, are installed with or before the diversions.
- Diversions should not be placed on slopes greater
than fifteen percent.
Level Spreaders
Level
Spreaders are outlets for dikes and diversions
consisting of an excavated depression constructed
at zero grade across a slope whereby concentrated
runoff may be discharged at non-erosive velocities
onto an undisturbed area stabilized by existing vegetation.
Their purpose is to convert concentrated runoff to
sheet flow and release it onto an area stabilized
by existing vegetation. This practice applies only
in those situations where the spreader can be constructed
on undisturbed soil and the area below the level lip
is stabilized by natural vegetation. The water should
not be allowed to reconcentrate after release.
- Level spreaders should be constructed on undisturbed
soil (not fill material).
- The entrance to the spreader should be shaped in
such a manner as to insure that runoff enters directly
onto the 0 percent channel.
- The level lip should be constructed on zero percent
grade to insure uniform spreading of storm runoff.
- The released runoff should outlet onto undisturbed
stabilized areas in sheet flow and not be allowed
to reconcentrate below the structure.
|