A "work area" is an area, defined by,
the limits of which shall be established by the Contractor
with the approval of the Project Engineer prior to
commencement of work.
|
| 4.2.1
Preparing Access and Staging Areas |
|
| < back to top >
|
Several principles should guide design, placement,
and construction of site access to ensure environmental
stewardship:
Avoid any sensitive wildlife habitat or plant areas
or threatened and endangered species and their designated
critical habitat.
Avoid crossing streams if at all possible; where
crossing is unavoidable, use bridges.
Minimize slope disturbance since effective erosion
control is difficult on a sloped roadway that should
be heavily used.
Construct roadways with low gradients; ensure that
stormwater runoff drains to outlets; install an adequate
roadbed; and, if possible, set up a truck-washing station
at the entrance of the construction site to reduce
offsite transport of mud and sediment by vehicles.
Every effort should be made to minimize and, where
possible, avoid site disturbance. Emphasis should be
placed on addressing protection of existing vegetation
and sensitive habitat, erosion and sediment control,
protecting air and water quality, protecting cultural
resources, minimizing noise, and providing for solid
waste disposal and worksite sanitation. Thus:
- Limit the types of construction operations, including
access and hauling, allowed in certain areas of the
project that may be more susceptible to erosion. For
example, do not allow unlimited vehicle crossing of
streams: provide a temporary crossing at a single
location and only when access is necessary.
- Plan and designate areas that are not to be disturbed
at all, or at which phase in the project the area
is to be disturbed. This can include limiting the
type of access or operation in a given area. For example,
consider only hand clearing operations in areas susceptible
erosion and fencing off areas that are not to be disturbed.
The benefits in limiting disturbed areas during construction
are fourfold:
- Maintaining existing vegetation preserves natural
habitats that reduce the potential impact of the existing
highway
- Areas left undisturbed may not warrant any pollution
prevention practices since their erosion potential
may not increase
- Existing vegetation can be utilized as an erosion
control device acting as a vegetative buffer filtering
and settling out sediment
- Smaller disturbed areas are more manageable when
trying to control runoff and erosion
|
| 4.2.2
Construction Phasing, Sequencing, or Acceleration |
|
| < back to top >
|
There are a variety of reasons for construction
sequencing. On environmental, restoration, or bioengineering
projects, sites often require earthwork as part of
site restoration and/or before installing a soil bioengineering
system. It is important to plan for and manage timing
conflicts that can occur between scheduling heavy equipment,
hand labor work, plant collection, and plant use.
One of the largest and most common environmental
stewardship concerns that can be addressed by construction
sequencing is minimization of unprotected soil and
resultant erosion and sedimentation. Construction sequencing
should be scheduled to minimize land disturbance at
all times, but especially during the rainy or winter
season. Scheduling should be considered when establishing
permanent vegetation ( appropriate planting time for
specified vegetation ) . The following environmental
stewardship practices are recommended:
- Minimize the extent and the duration of exposure
of bare ground surface to be opened at any one time,
to prevent erosion at the source. Limiting the area
of erodible soil exposed at any given time also helps
sustain a manageable area of construction activities.
- Plan the phases or stages of construction to minimize
exposure. On larger projects, sub-phases should be
used to minimize the area of exposed soil. Before
site disturbance occurs, perimeter controls, sediment
traps, basins, and diversions should be in place to
control runoff and capture sediments. Prioritize disturbed
areas in the vicinity of water bodies, wetlands, steep
grades, long slopes, etc. for effective stabilization
within seven days of disturbance.
- Complete and employ permanent structures, controls,
and stabilized areas as soon as practical for use
as erosion and sediment control measures for the remaining
construction operations. For example, grade and revegetate
ditch early on in the project so they can assist in
reducing the effects of later construction operations.
- Schedule land-disturbing activities during periods
of low precipitation.
- Complete grading as soon as possible after it is
begun.
- Maintain the maximum amount of existing vegetation
to assist in the control of and to minimize the exposed
erodible area. For example, do not clear or grub an
area until work is necessary.
- Establish permanent vegetative cover immediately
after grading is complete. Graded areas that will
not be worked on should be seeded and mulched immediately,
rather than waiting until all project grading is done.
- Monitor work to ensure progress according to the
schedule and adjustments if necessary. When changes
are warranted, amend the sequence scheduling in advance
to maintain sediment control.
The Nova Scotia Transportation and Public Works has
further defined the requirements for work area and
construction phasing, to ensure that construction phasing
does not become the weak link in erosion and sedimentation
control: [N]
- The size of the work area is determined by the
grading, seeding and final slope protection the Constructor
can complete within 30 calendar days. Such grading
should include completion to the lines and grades
shown on the plans, to prevent re-work.
- Work will be considered started with grubbing
and will be considered complete when the specified
cover material is applied ( e.g., straw/hay/compost/bark
mulch, erosion control blanket, Clear Stone, sod,
hydroseeding).
- Work
Progression Schedule and Contingency Plan for
failure of Erosion and Sedimentation Control measures
shall be completed by the Contractor and approved
by the Project Engineer prior to commencement of
any grubbing.
- Plan for unforeseen circumstances ; if
conditions are encountered in an active work area
which requires extra care or work which the Contractor
is unable to continue at that time, the Contractor
will be allowed to open up additional work area(s)
with the approval of the Project Engineer only after
the original work area is temporarily protected, i.e.,
straw/hay/compost/bark mulch. If unforeseen circumstances
occur, the 30 calendar day period may be extended
with the approval of the Project Engineer. This extension
must be accompanied by a written report outlining
the need for the extension and the measures to be
taken to control erosion and sedimentation. Inconvenience
to the Contractor, poor planning or not having adequate
or appropriate equipment will not be considered unforeseen
circumstances.
- Identify measures for non-compliance .
Once the grubbing operation within a specific work
area has begun, work shall be continuous from grubbing
through to the placement of seed (including fertilizer,
lime) and final slope protection, where required.
If after 30 calendar days the above described work
is not completed, then: (a) No additional work area(s)
will be allowed to commence until these work areas
are completed; and (b) All work areas will be immediately
protected with straw/hay or compost/bark mulch. If,
in the Project Engineer's judgment, there is non-compliance
with erosion and sediment control provisions or if
the Contractor receives a warning or citation from
DEL or DFO, then corrective action may require a shutdown
of construction activities, until such time as the
non-compliance is satisfactorily corrected.
EPA has also developed a Fact
Sheet on Construction Sequencing, available on-line.
Grade Management
Proper planning and management of highway construction
grading operations can significantly lower the erosion
problems associated with these activities. No operation
in highway construction increases the potential for
erosion as much as excavation and embankment activities.
The erosion potential of an area is increased as erodible
areas are exposed and slopes are steepened and lengthened.
The following is a list of items to consider when managing
grading operations: [N]
- Excavation and embankments should be completed
to final grade and stabilized in a continuous operation;
piles of loose material should be minimized at all
times.
- Offsite flow should be prevented from crossing
into excavated areas by intercepting and/or diverting
flows into and through undisturbed or controlled areas.
- Perimeter controls should be installed at the toe
of the slope in embankment sections to prevent sediment-laden
runoff from leaving the site.
- Small berms or dikes should be placed at the end
of each days grading operations in cut and fill sections
to divert or intercept runoff to controlled areas.
- Prompt grading and stabilization of ditches will
greatly reduce the potential sediment load.
|
| 4.2.3
Preserving Local Fish and Wildlife through Attention
to Timing Restrictions |
|
| < back to top >
|
Timing restrictions might be imposed on the
project due to the presence of nesting, migrating,
or wintering threatened or endangered species. Restrictions
are dependent upon the distance from the species'
activity center, the type of activity proposed,
and the time of year the activity is proposed. Pile
driving, blasting, and other noise generating activities
(addressed in Section 4.9, Noise Minimization) are
of the greatest concern.
Timing restrictions might also be placed on projects
involving construction in or over water, such as
culvert or bridge installation or pile driving.
Sensitive times include winter periods, migratory
periods, and breeding seasons.
During construction, clearly flag or place construction
fencing around all habitat areas and features that
are to be saved or avoided in the field, and include
those locations in the plans of the project. This
will minimize confusion and will help avoid impacting
these areas and/or features.
Projects near stream or wetland habitat areas
must have their erosion control measures carefully
implemented and maintained during construction to
avoid impacting aquatic species.
Occupied migratory bird nests may not be removed;
however, nests can be covered prior to seasons when
nests would be re-occupied.
See section 7.2, Avoiding
and Minimizing Impacts to Fish and Wildlife and
Enhancing Habitat for further discussion of timing
restrictions.
|
| 4.2.4
Accelerated Construction |
|
| < back to top >
|
Though accelerated construction is often driven
by increasing traffic demand, this practice is also
highly useful to minimize environmental impacts on
certain projects as it focuses on "getting in
and getting out" as quickly as possible. Sponsored
by the American Association of State Highway and Transportation
Officials' (AASHTO) Technology Implementation Group
(TIG) and the Federal Highway Administration (FHWA),
the Accelerated Construction Technology Transfer process
begins with a 2-day workshop in which a multidisciplinary
team of 20–30 national transportation experts
works with an equal number of their local counterparts
to evaluate all aspects of a project and develop recommendations
for reducing construction time and enhancing safety
and quality. [N]
Transportation Research Board Task Force A5T60 on
Accelerating Innovation was formed in 1999 to promote
accelerated construction in the highway infrastructure.
In 2002, the task force completed two ACTT pilot workshops
in Indiana and Pennsylvania. AASHTO-TIG and FHWA are
continuing the effort, and workshops in Texas, Louisiana,
and California were conducted in 2003. Interest among
State highway agencies has been very high, and six
workshops already are occurring in 2004. Recent workshop
recommendations have included using design-build contracting;
coordinating with utility companies early in the project
planning process; using long-life pavements with a
50-year design lifespan; improving general materials
specifications; establishing a dedicated incident management
system at the project site; and introducing various
traffic flow strategies. In some cases project construction
times have been cut in half. [N]
|
| 4.2.5
Pre-Contract and Pre-Construction Activities |
|
| < back to top >
|
Emphasize sensitive areas during precontract
meetings. Note the kinds of activities that are
not allowed in the sensitive areas and designated
lands (such as clearing, grading, stockpiling materials,
construction equipment, vehicle parking, etc.). This
will help to minimize confusion and also help contractors
and construction personnel avoid the sensitive areas.
Items that should be specifically addressed at the
prework meeting include: [N]
- Access ― Equipment access points that minimize
disturbance, especially to less stable areas should
be located.
- Protection of Water Quality – Prevention
of direct runoff of sediment containing water into
streams, proactive prevention of erosion, qualitative
design expectations relating to construction area
drainage and treatment, preparation and protection
of the site from potential storms during the work
period.
- Protection of Habitat – Preservation of riparian
habitat, minimization of damage to existing vegetation,
preservation and use of cleared large wood with stumps.
- Dewatering Method Performance - Expectations of
erosion control methods, sediment trapping and turbidity
treatment of runoff, expectations of possible subsurface
flow in the excavation and the method for handling
it, including payment method. Capture and rescue of
aquatic organisms may be an important part of dewatering
that could be the responsibility of the contractor.
Discuss expectation and coordination with other specialists
(fish biologist).
- Quality of Stream Bed Simulation Rock Placement – Emphasize
that the intent is to reconnect the channel and create
as natural a channel inside the pipe as possible.
Photos of the site showing stream segments with similar
channels to what is in the contact plans can be helpful.
Discuss the proposed method of placing of bed material;
this often requires hand labor and specialized equipment.
The quality of labor and effort put into fitting and
interlocking individual pieces of rocks together can
have a substantial effect on their durability. Material
dimensions, gradation, and permeability are vital
to the simulated streambed's performance. Special
specification and pay items are vital to describe
and administer this area of work. These items may
be a minor cost item in the overall contract, but
they have a major impact on the effectiveness of the
structure.
Perform construction surveys if needed for bioengineering
projects. Additional surveys by the contract administrator
may be helpful before excavation to help locate any
additional specific features or objects not in the
contract drawings or original survey. Surveys performed
during construction to determine specific locations
of the structure and details are extremely important
and are in a larger sense verifying that the design
meets the site geometry. Contractor survey accuracy
should be checked. Contract administrator should be
skilled in survey methods and able to verify contractor
surveys. Survey errors can lead to costly construction
mistakes and, therefore, should be caught as soon
as possible. For instance, if the structure is placed
at the wrong elevation, when the stream channel is
constructed and reconnected to the adjacent channel,
slopes into or out of the pipe may cause channel scour
or passage problems that are difficult to mitigate.
A structure placed in the wrong location may create
road alignment problems later on.
Confine construction and staging areas to the
smallest area necessary. Construction area boundaries,
including staging areas, should be clearly marked
to ensure and all construction activity and storage
of construction materials should occur within these
marked areas.
- Use disturbed or developed areas for staging whenever
possible.
- Keep right-of-way for watercourse crossings as
narrow as possible within the constraints of safety
and construction requirements. Limit removal of vegetation
to the width of the right-of-way.
- Where possible, plan instream work to occur as
a single event.
- Restrict instream work to low flow periods where
possible.
- Limit machinery access to a single point on one
bank.
- Limit distance between machinery access point and
work site.
- Utilize new technologies such as prefabricated
materials and Geosynthetic Reinforced Soil abutments
and walls to minimize the access needed for large
equipment.
Install construction fencing or flagging to protect
sensitive areas from encroachment by construction
activities, if appropriate. As in delineating work
zones, fencing should be placed around all protected
areas during initial site preparation, even before
the access road is fully constructed, if possible,
but certainly before wholesale earthmoving begins.
Fencing material should be easy to see, and areas
should be labeled as protection areas.
Delineate and mark wetland areas. Adjacent
or nearby wetland areas not in the construction area
should be fenced to reduce potential impacts from construction
activities. Consider the following as indicators of
possible wetland presence, and a potential "red
flag" until the area is delineated by a trained
wetland biologist:
Wetland Hydrology Indicators
- Areas that have standing water at any time of
the year.
- Topographical low areas.
- Areas near streams, lakes, or other shorelines.
- Areas with water seeping out of a hillside.
- Ditches that hold water long after rain events.
- Ditches that flow to other water bodies such as
streams, lakes, ponds, and the like.
Wetland Soil Indicators
- Areas where vehicles get stuck or leave ruts.
- Areas with dark, sticky soils.
- "Unsuitable soils" for construction
or foundation.
- Highly organic soils.
- Clay soils that are pale gray or mottled.
- Sites within floodplains.
- Soils that give off a rotten egg smell when disturbed.
Wetland Vegetation Indicators
- Obvious wetland plants such as rushes or cattails.
- Trees such as alders or willows dominating low-lying
areas.
- Shrub Thickets in low-lying areas.
Isolate the work area from other jurisdictional
waters.
Prevent discharge of water from the work area
prior to treatment. All runoff from the work area
should drain through a Sedimentation Control BMP or
a Dewatering Device BMP prior to entering jurisdictional
waters.
Maintain a buffer area along streams and other
waters of the state or waters of the U.S. Buffers
are areas along jurisdictional waters such as streams,
lakes, ponds and estuaries that often have legal protection.
A typical riparian buffer is a 50-foot wide vegetative
strip along each side of a jurisdictional stream measured
from the top of bank or the mean high water line.
The riparian buffer typically cannot be disturbed
unless specific conditions are satisfied. Existing
drainage ditches and roadside ditches are typically
exempt from the buffer rules provided that they are
managed to minimize sediment, nutrients and other
pollution that enters jurisdictional waters. Existing
drainage ditches may not be deepened beyond original
pre-construction depths. New ditches through a riparian
buffer are typically not allowed unless specific conditions
are satisfied. [N]
|
| < back to top >
|
| |
|
| |
|